Shoreditch update 5th September 2001Finally, we got it says Trevor ParsonsGood news. Two-way general traffic in Shoreditch High Street has been accepted as the goal by all now. It's just that we'll have to wait until a second phase of implementation to get it. Great Eastern Street will be two-way for all traffic. Even Old Street will be two-way for all traffic. But Shoreditch High Street will, in phase one of implementation, be semi-two-way, with a northbound contraflow for buses and bikes, and the rest of the northbound traffic continuing to be diverted via Curtain Road. What lies between us and the ultimate aim are some strands of optical fibre outside the telephone exchange on Shoreditch High Street. Transport for London (TfL), which is now taking forward the reform of the past-its-sellby-date 1960s one-way system, has been quoted millions to move them, in order to remove the pinch point which is the only thing stopping a return to full two-way traffic in Shoreditch High Street. This figure will probably go down, but there isn't a budget to do this work in the current timescale (on site January 2002), so it'll have to wait for another year or so. Among the many improvements made to the scheme as a result of the public consultation on TfL's first draft, we were shown several improvements to cycle permeability, including a toucan crossing (ie for both pedestrians and cyclists) at the desire line we demonstrated during the Look Both Ways event last December, across Shoreditch High Street between Boundary Passage and New Inn Yard. Other major stuff:
Reform of Shoreditch Triangle One Way SchemeUpdate bulletin by Roland Jeffery A follow-up meeting was held yesterday 13 August 01 between TfL officers ands several community representatives and with the participation of LBHackney. This was initially proposed by TfL in order to discuss TfL's responses to their public consultation exercise on the scheme.
Update on the Scheme
Under the revised scheme Curtain Road would continue to take northbound traffic as at present - except that busses will go up Shoreditch High St. Two way traffic is not found to be feasible in Shoreditch High Street. The volumes of traffic in Curtain Road would not be greater than now and the wider pavements, reduction from 4 to 2 lanes and a new crossing at Riving ton St should make it a lot nicer to walk along and make the traffic slower/ better behaved. There was discussion about this aspect. Apparently two way traffic in the High Street has come across a problem with fibre optic cables under the footway at a key pinch point and the cost of moving these is prohibitive at present. However TfL think two-way working is otherwise possible - if the cables can be moved. That is now planned as phase II of the scheme. TfL officers went on record as saying that moving the cables to enable two way working in Shoreditch High Street is a clear medium term objective Nothing else in this phase ( which can now be called Phase I) would be abortive if phase II gets the go-ahead when money becomes available to move the fibre optics, Curtain Road would then become a minor distributor road and all the northbound traffic - not just busses - would go up Shoredtich High Street. This is the first time those at the meeting had heard about the problem of the fibre optics route underneath the High Street. LBH officers present confirmed that it was a serious problem and relocation of the cables was very expensive - relative to the overall budget for the rest of the scheme.
Fine Tuning
Works have already started
Traffic volumes
The main works are timetabled to go on site Jan 2002 and be finished by the end of 2002. There will be even more serious delays due to main works, but the broad principle is that traffic will run in the present pattern during works, albeit on roads limited by lane closures. The Mayor's Congestion Charging scheme is not now premised on toll booth style cameras at the gateways to the central area, but on cameras, many of them mobile, throughout the charge area. Therefore the Triangle Scheme can go ahead as designed. Works to Commercial Street immediately to the south of the Triangle will start soon, whilst gating of traffic at Old St Roundabout will be introduced by means of newly installed traffic lights, also to go up in 2002.
15 August 01 Shoreditch Town Hall Trust www.shoreditchtownhall.org.uk Read up on a bit of history on the reform scheme.
|
